Everything was behavioral until the last maybe 10 minutes, where I was asked what steps I would take to maximize some product's output. Even though I didn't know lean terms such as takt time, the interviewer explained what it was, and I was able to answer the question.
Interview questions [1]
Question 1
What are some things you would if your cycle time was 120 seconds and your takt time was 60 seconds on your production line?